Rule 21 Phase 1 July 26th Changes 1P and 3P

Created by Victor Herrera, Modified on Thu, Jun 9, 2022 at 10:47 AM by Victor Herrera

 Single Phase / Three Phase - Note Step 7 Differences 

 

Please follow all local safety standards 

 

This method of procedure has been created to assist all installers in setting the Ginlong Solis Inverters to comply with Rule 21 Phase 1 July 26th changes. This change can only be completed on all Ginlong Solis Rule 21 compliant inverters. For any questions please contact our service line at 866-438-8408. 

 

Step 1: Turn the inverter on with DC Voltage Only 

 

Step 2: Go to the Advanced Settings in the Menu 

 

 

Step 3: Grid On/OFF and set Grid to OFF 

 

 

Step 4: Go to STD. Mode Settings 

 

 

Step 5: Go to Working Mode Set 

 

 

Step 7 Single Phase: Set the settings as follows: 

  • V1 – 220 

  • V2 – 232 

  • V3 – 247 

  • V4 – 256 

  • Q1 – 30% - Default 

  • Q2 – 30% - Default 

Step 7 Three Phase: Set the settings as follows: 

  • V1 – 255 

  • V2 – 268 

  • V3 – 286 

  • V4 – 297 

  • Q1 – 30% - Default 

  • Q2 – 30% - Default 

 

 

Step 8: Hit Escape 

 

Step 9: Save and Send 

 

Step 10: Go to Grid On/OFF and turn the grid back on. 

 

Step 11: Complete your commissioning process. 

 

 

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article